D3. SCOPE OF WORK
D3.1 The Work to be done under the Contract shall consist of four parts:
(a) Part 1 – City Funded Work
(b) Part 2 – Water and Waste Work
(c) Part 3 – Traffic Signals Work
(d) Part 4 – Manitoba Hydro Funded Work
Part 1 – City Funded Work
D3.2 Part 1 – City Funded Work shall consist of:
(a) Asphalt Pavement Reconstruction
(i) Burnell Street from St. Matthews Avenue to Ellice Avenue;
(ii) McMicken Street from Ellice Avenue to Sargent Avenue
(iii) Kennedy Street / Edmonton Street Alley from York Avenue to St. Mary’s Avenue;
(iv) Langside Avenue from Cumberland Avenue to Notre Dame Avenue;
(b) Major Concrete Pavement Rehabilitation
(i) Qu’Appelle Avenue from Balmoral Street to Kennedy Street; and
(c) Minor Concrete Pavement Rehabilitation
(i) McGee Street from St. Matthews Avenue to Ellice Avenue.
Part 2 – Water and Waste Work
D3.3 Part 2 – Water and Waste Work shall consist of:
(a) Manhole Repairs
(i) McGee Street
(b) Sewer Repairs
(i) McGee Street
Part 3 – Traffic Signals Work
D3.4 Part 3 – Traffic Signals Work shall consist of:
(a) Traffic Signals
(i) Burnell Street at St. Matthews Avenue
Part 4 – Manitoba Hydro Work
D3.5 Part 4 – Manitoba Hydro Funded Work shall consist of:
(a) Street Light Installation
(i) Burnell Street from St. Matthews Avenue to Ellice Avenue
The City currently has no approved funding in the Capital Budget for Part 4 of the Work, but is
anticipating receiving notification about funding from Manitoba Hydro by late May 2025. Part 4 of
the Work is contingent upon Manitoba Hydro approving sufficient funding.
D3.6 The major components of the Work are as follows:
(a) Asphalt Pavement Reconstruction
(i) Removal of existing sidewalk;
(ii) Planing of existing asphalt at intersections as required;
(iii) Renewal of existing concrete sidewalk as required;
(iv) Tree stump grinding;
(v) Construction of 100mm concrete sidewalk;
(vi) Installation of detectable warning surface tiles;
(vii) Removal of existing pavement;
(viii) Removal of existing curb;
(ix) Abandon existing catch basins and drainage inlets;
(x) Installation of catch basins and sewer service pipes;
(xi) Installation of subdrains;
(xii) Excavation;
(xiii) Compaction of existing sub-grade;
(xiv) Adjustment of existing pavement and boulevard structures;
(xv) Placement of separation geotextile fabric and Type A geogrid;
(xvi) Placement of sub-base material (placed in two lifts);
(xvii) Placement of base course material;
(xviii) Installation of Traffic Signals conduit, service boxes, and concrete bases;
(xix) Construction of select curb types for asphalt pavement, utilizing slip-form paving
equipment;
(xx) Construction of modified barrier curb with reversed gutter for asphalt pavement;
(xxi) Construction of curb ramp for asphalt pavement;
(xxii) Construction of 150mm concrete pavement (plain-dowelled) for inlet isolations for
asphalt pavement;
(xxiii) Construction of modified barrier curb;
(xxiv) Construction of curb ramp;
(xxv) Construction of 40mm lip curb (separate);
(xxvi) Renewal of existing curb as required;
(xxvii) Renewal of existing curb ramp;
(xxviii) Renewal of existing curb and gutter as required;
(xxix) Boulevard restoration and sod;
(xxx) Placement of asphalt pavement (Type MS2, 55mm thickness);
(xxxi) Placement of asphalt pavement (Type MS1, 70mm thickness);
(xxxii) Placement of asphalt pavement tie-ins;
(xxxiii) Planing or removal of existing asphalt for asphalt speed hump; and
(xxxiv) Construction of asphalt speed hump, as required.
(b) Concrete Pavement Rehabilitation (Major/Minor)
(i) Removal of existing asphalt, as required,
(ii) Renewal of existing concrete sidewalk;
(iii) Excavation;
(iv) Compaction of sub-grade;
(v) Installation of geotextile;
(vi) Placement and compaction of sub-base material;
(vii) Installation of geogrid;
(viii) Placement and compaction of base material;
(ix) Construction of new concrete sidewalk;
(x) Renewal or construction of curb ramps;
(xi) Installation of detectable warning surface tiles;
(xii) Abandoning existing drainage inlets;
(xiii) Removal of existing catch pits;
(xiv) Installation of new catch pits;
(xv) Installation of new catch basins;
(xvi) Connecting new pipe to existing sewer or existing catch basins;
(xvii) Repair of existing catch basin leads;
(xviii) Full depth concrete repairs of existing slabs and joints;
(xix) Adjustment of existing pavement and boulevard structures;
(xx) Renewal of existing curb as required;
(xxi) Construction of modified barrier curb;
(xxii) Boulevard grading;
(xxiii) Placement and compaction of topsoil;
(xxiv) Installation of pavement repair fabric (Type B);
(xxv) Placement of main line asphalt pavement overlay (Type MS1);
(xxvi) Placement of asphalt pavement at tie-ins and approaches (Type MS1); and
(xxvii) Placement of sod.
(c) Water and Waste Work
(i) External point repairs to existing sewer mains
(ii) Replacement of manhole risers
(iii) External point repairs of existing sewers;
(iv) Repairs to manhole structures; and
(v) Sewer and sewer service video inspection.
(d) Traffic Signals Work
(i) Installation of traffic signals conduit, service boxes, and concrete bases.
(e) Street Light Installation
(i) Installation and removal of temporary overhead spans;
(ii) Removal of existing street light poles and bases;
(iii) Installation of new pre-cast concrete bases including luminaires and appurtenances;
(iv) Installation of new street lighting cables in conduit (boring) and street light poles,
including cable termination; and
(v) Installation of ground rods.