DEFENCE CONSTRUCTION CANADA (DCC) – Project No. HAAGW15_83783 – Servicing Furnaces, Smoke Detectors, HRV & Heat Pumps, 14 Wing Greenwood, NS
The work includes, but is not necessarily limited to, the supply of labour, material, supervision, and equipment necessary to complete the cleaning, inspection, servicing and repair of Heat Recovery Ventilators (HRV's), Oil Fired Furnaces and Furnace / Heat Pump combo units, Smoke Alarms and Smoke Alarm / Carbon Monoxide combo units and Heat Pumps in Residential Housing Units (RHU's) within Costello Park, Greenwood, Nova Scotia.
A site visit has been arranged for the following date, time, and location. It is highly recommended that bidders attend this visit.
Date: March 20, 2025 March 25, 2025
Time: 10:00am, local time
Location: 13 8th Crescent, Greenwood, NS B0P 1N0
The estimated cost for this opportunity is in the range of $301,000.00
The Work must be completed no later than 364 calendar days after notification of contract award.
Questions regarding this solicitation are to be directed ONLY to the point of contact identified in this advertisement. Bidders who address their questions to anyone other than the point of contact during the solicitation period may, for that reason alone, be disqualified.
Please note that the preliminary tender results for this project will be available on MERX.
Bidders can obtain contract award results from the DCC website at https://www.dcc-cdc.gc.ca/industry/contract-activity.